"RENET" PE

"RENET" PE

 

Project start - November 2016, finish – September 2017.

Project goal: Serum concentration line with productivity 9000l/h.

Scope of supply:

  • harmonization of production technology;
  • calculation and selection of equipment;
  • determination of the required area;
  • location of equipment, identification of points of approach and removal of service media, location of sewer trays;
  • manufacture and assembly of units;
  • installation-supervision of the line into the Customer.