"Loostdorf" Ltd.
1. Project 2017.
Project goal: Production of processed cheese and desserts.
Scope of supply: Selection and delivery of the "Stephan" melting pot and the "Alfa Laval" deaeration module.
2. Project 2016.
Project goal: Fermentation of dairy products.
Scope of supply: Selection and delivery of the "Schwarte-Milfor" tanks.
3. Project start - June 2008, finish – December 2011.
Project goal: 1st phase of production reconstruction and extension. Milk treatment increasing and production growth.
Scope of supply: Project management, consulting and coordination, engineering arrangement, constructure, logistic, technology, energy supply, equipment, installation and commissioning.
Summary:
- new "ice water" supply system;
- new water treatment system and water distribution system, including recycling water;
- new boiler;
- new electricity supply system;
- new system of internal and external sewage systems;
- new filling machines and processing lines;
- new butter production department;
- new dry milk powder production;
- new constructions and reconstruction of existing buildings;
- start of project for waste water treatment.